RSA 362-I:2 Procurement of Renewable Natural Gas and Investment in Renewable Natural Gas Infrastructure by Gas Utilities.
Title: XXXIV - PUBLIC UTILITIES
Chapter: 362-I - PROCUREMENT OF RENEWABLE NATURAL GAS
I. The commission may approve, upon the filing of a petition by a gas utility, recovery of costs related to prudent utility procurement of renewable natural gas and any qualified investment, including the use of an associated cost recovery mechanism, if the commission determines that it is in the public interest to do so after notice and hearing pursuant to RSA 541-A.
II. Determination of the public interest under paragraph I shall include consideration of, and each utility filing pursuant to this chapter shall include a detailed description of, the following:
(a) The monetary benefits of the proposal to the utility customers and the state, such as the value of any environmental attributes or carbon offsets, relative to the incremental cost to gas utility customers neces