RSA 162-R:3 Energy Infrastructure Proposal Application Process.
Title: XII - PUBLIC SAFETY AND WELFARE
Chapter: 162-R - ENERGY INFRASTRUCTURE DEVELOPMENT AND CORRIDORS
I. (a) To initiate the application process, a developer may file with the department of transportation, a request for a preliminary conceptual feasibility study, including such project-specific information as the department may specify in accordance with the department's utility accommodation manual.
(b) Within 30 days after such study request is filed, the department shall provide written notice to the developer, with a copy to the site evaluation committee, either accepting such study request as sufficiently complete to allow the department to evaluate the conceptual feasibility of the proposal and submit its recommendation to the committee, or specifying the additional information needed to complete its evaluation.
(c) Upon notice to the developer that the study reque